Receipt Date

Receipt Date

Receipt Date

Many trading partners calculate their effective date from the date they received the pallets.  PalletWatch applies a very basic transit days calculation when you raise a transfer off, e.g. if going from NSW to Victoria then 1 transit day would be added to the despatch date and this becomes the Scheduled Receipt Date.

This Scheduled Receipt Date may not be accurate as the delivery may have a timeslot on a different date or the receiving site may not work on weekends, etc.  To improve the accuracy of the Scheduled Receipt Date you could do the following:
  1. If you raise the docket before the Despatch Date then ask users to ensure that they select the correct despatch date - not the one which automatically appears.
  2. When creating an off docket click on Auto in the Receipt Date field.  This will change the Auto button to read Manual.
  3. Select the date you believe the delivery will be made.  This could be sourced form the customer's delivery instructions on their documentation.
An alternative to this could be to change the delay days but this may not work for the following reasons:
  1. Receivers may only look at the Scheduled Receipt Date on the docket.  Changing delay days or the Effective Date will not change the Scheduled Receipt Date so it will still appear as being incorrect to the receiver.  E.g. if you change Woolworths delay days from 30 days to 31 the Woolworths receiver will enter the actual date received so you could end up giving Woolworths 32 days instead of 30.
  2. If CHEP equipment is involved then an EDO (Equipment Days Offset) could be in place and thus you cannot change the delay days as CHEP applies them automatically.

    • Related Articles

    • Transit Days

      Transit Days - Trading Partners Transit days are the number of days travel between two sites. PalletWatch automatically calculates transit days based on preset days in the database, e.g. 2 days from VIC to QLD, 1 day from VIC to NSW, etc. ...
    • Changing Despatch Date

      Changing Despatch Date If you change the despatch date on a transfer off docket then you need to ensure the following: The Receipt Date should not be earlier than the Despatch Date. If the Receipt Date is set to Manual then click on the Manual button ...
    • Transfer Off Receipt Date

      Transfer Off Receipt Date PalletWatch calculates the receipt date based on preset transit days.  If you receive date corrections from your trading partners then it may be that the receipt dates are not correct.   CHEP corrections can read as 412 - ...
    • Delay Days

      Delay Days A delay day transfer is where the transfer of hire is delayed. The delay can be from the date of despatch or the date of receipt. E.g. a 30 day delay day transfer from the date of receipt means that the sender continues to pay hire on the ...
    • Effective Dates

      Effective Dates The Effective Date is the date when the transfer of equipment takes place. The movement date could be different to the Effective Date, when this happens the transfer of equipment has been delayed until the Effective Date. Loscam ...